省道215线康定瓦泽至九龙公公路改建工程A5合同段
鸡丑山隧道洞口 截水沟施工方案
道隧集团工程有限公司 编制:
审核:
审批:
2012年5月1日
省道215线康定瓦泽至九龙段公路改建工程A5合同段 隧道洞口截水沟工程
目 录
2012年5月1日 ····································································································································································· 1 1、工程概况 ·································································································································································································· 2 2、编制依据 ·································································································································································································· 2 3、施工管理人员及施工队伍安排 ·························································································································································· 2 4、施工人员、机械设备配置 ··································································································································································· 3 4.1 施工人员配置 ·········································································································································································· 3 4.2 机械设备配置 ·········································································································································································· 4 5、施工工艺与流程 ····················································································································································································· 5 5.1 施工顺序 ·················································································································································································· 5 5.2 具体施工步骤 ·········································································································································································· 5 6、质量保证措施 ························································································································································································· 5 7、安全保证措施 ························································································································································································· 5 8、环境保护措施 ························································································································································································· 6 8.1组织措施 ··················································································································································································· 6 8.2防止大气污染措施 ·································································································································································· 6 8.3防止施工噪声污染措施 ·························································································································································· 6
1 道隧集团有限公司
省道215线康定瓦泽至九龙段公路改建工程A5合同段 隧道洞口截水沟工程
1、工程概况
鸡丑山隧道位于鸡丑山越岭段,原有省道215线为克服高差,多次回头展线,且高海拔地区,受冰雪期、雾期及冻土路基影响较大,行车安全性较差。本次改建采用2745m的长隧道穿过,既降低了原路海拔约300m,,又避开了冰雪及雾区期较长的路段。
隧道进洞口表层为第四系全新统残坡积的碎石,岩体裂隙发育,部分裂隙泥质充填,钻孔见裂隙为石英脉充填。隧道挂扣、成洞条件差,地下水活动较弱,洞室一般潮湿,雨季施工时有滴水或线状水流。
隧址区属青藏高原气候,夏季温和、冬季寒冷。多年平均降水量906mm,一般集中在6—9月;年平均气温1.1℃,1月平均气温<-7℃,无霜期约90天。 2、编制依据
(1)A5标段隧道设计图; (2)本标段的施工组织设计; (3)现行施工规程、规范、法规; (4)洞口现场勘察情况。 3、施工管理人员及施工队伍安排
(1)施工领导小组: 组 长: 副组长: 组 员:
(2)领导小组岗位职责:
XXX:全面负责组织施工管理工作及施工队伍落实工作,是安全责任第一人。 XXX:具体负责现场施工生产、安全、质量的指挥、协调及队伍的组织工作。
2
道隧集团有限公司
省道215线康定瓦泽至九龙段公路改建工程A5合同段 隧道洞口截水沟工程
XXX:负责技术及质量组织管理工作,负责审定施工方案、计划和质量控制技术管理工作。 XXX:根据施工方案,做好材料的计划及采购工作。
XXX:负责施工现场管理工作,施工方案的编制及落实隧道洞口边坡施工期间的质量、安全和环保措施工作。
XXX:协助郑雷负责现场施工管理工作。
XXX:全面负责现场边坡喷锚防护的质量保证措施的实施、检查与控制。 XXX:全面负责施工测量工作的放样、测量检验工作。
(3)施工队伍:组织一个施工队,负责耿家庄隧道洞口截水沟施工。 4、施工人员、机械设备配置
4.1 施工人员配置
⑴管理人员
①工区负责人:5人; ②施工队长:4人;
③安全员:4人;质检员:2人;试验员:2人。 管理人员共计17人/工区。 ⑵作业班组
钻爆班25人,装动班10人,钢筋班20人,综合班12人,拌合站15人 班组小计82人/工作面。
施工班组分工及劳力安排计划
序号 班组名称 1 钻爆班 工作内容 担负钻孔、装药爆破、沟内排水。 2 装运班 装碴运输作业。 担负风水电供应,洞内高压风劳力安排计划 自制钻孔台车司机1名,凿岩工18名,锻钎工2名,普工4名,共25人。 装载机司机2名,自卸汽车司机8电焊工4名,空压机司机2名,抽7 综合班 管、通风管、水管接长,通风水泵站司机1名,普工5名,计12名。 3
道隧集团有限公司
省道215线康定瓦泽至九龙段公路改建工程A5合同段 隧道洞口截水沟工程
8 9 拌合站 合计 担负喷锚料砼及零星砼拌合机司机2名,运输车5名,普通工 82名 4.2 机械设备配置
主要施工机械设备进场情况
序设备名称 号 1 2 3 4 5 6 7 8 9 挖掘机 轮式装载机(侧式) 自卸汽车 凿岩机 风镐 注浆泵 强制式混凝土拌合机 滚筒式混凝土拌合机 混凝土湿喷机 PC200 ZL50C 东风5t YT-28 G-10 BW-250/50 JS500 350 TK961 L-120/20 各型 各型 台 台 辆 台 个 台 座 台 台 台 台 套 规格/型号 单位 配置数备注 量 3 3 6 20 10 2 2 2 4 8 4 2 10 电动空压机 11 污水泵 12 钢筋加工、焊接设备
4 道隧集团有限公司
省道215线康定瓦泽至九龙段公路改建工程A5合同段 隧道洞口截水沟工程
5、施工工艺与流程
5.1 施工顺序
首先在洞顶人工挖截水沟,并根据施工图设计要求进行铺砌浆砌片石,把雨水引出洞口施工作业区外。
5.2 具体施工步骤
(1)在开挖的边仰坡边线外5m,由测量组进行截水沟中线定位。 (2)按放好的中心线进行截水沟开挖,开挖净空符合设计要求。
(3)铺砌或混凝土浇筑之前,对边沟、截水沟进行修整,保证沟底和沟壁坚实平整,沟底标高及断面尺寸符合图纸要求。
(4)按要求铺设砂砾垫层,并夯压密实。
(5)沿沟壁纵向挂线,先铺砌沟底,再铺砌侧壁,保证铺砌时座浆饱满、沟缝平顺,铺砌成型的排水沟平整密实,沟底顺畅,不积水,并注意与洞口其它排水系统相结合,合理导流。 6、质量保证措施
测量(指中线与高程)控制的结果,除了直接影响到工程质量,还将直接影响建设成本和单位信誉。为此,我们将利用洞外导线点,实现洞门位置的准确,路基边坡放坡的准确。 7、安全保证措施
(1)严格执行安全管理制度,从管理上确保安全措施的落实。 (2)在高于3m的坡面上作业,必须挂安全绳。
(3)各种施工机械必须制定相应的、详细的操作规程,并严格执行。夜间作业时,应有足够的照明设备。
5 道隧集团有限公司
省道215线康定瓦泽至九龙段公路改建工程A5合同段 隧道洞口截水沟工程
(4)严禁截水沟和下方其它工程同时施工。 8、环境保护措施
为了保护和改善生活环境与生态环境,防止由于隧道施工造成的作业污染和扰民,保障工地附近居民和施工人员的身体健康,努力做好环境保护工作。
8.1组织措施
施工期间对环境进行保护是业主对承包商的要求,也是承包商的自身职责。根据公司管理标准、国家省市规定、业主要求,结合工程的具体情况制定本工程《环境保护实施细则》,以细则的各项具体规定作为统一和规范全体施工人员的行为准则。
同时,委派专门的环境保护工作人员,全面负责本项目的环境保护工作。
加强环保教育和激励措施,把环保作为全体施工人员的上岗教育内容之一,提高环保意识。对违反环保的班组和个人进行处罚。
8.2防止大气污染措施
(1)清理施工垃圾时使用容器吊运,严禁随意临空抛撤造成扬尘。施工垃圾及时清运,清运
时,适量洒水减少扬尘。
(2)施工道路采用硬化,并随时清扫洒水,减少道路扬尘。
(3)工地上使用的各类柴油、汽油机械执行相关污染物排放标准,不使用气体排放超标的机
械。
(4)搅拌站设置封闭的搅拌棚,在搅拌机上设置喷淋装置。
8.3防止施工噪声污染措施
(1)作业时尽量控制噪音影响,对噪声过大的设备尽可能不用或少用。在施工中采取防护等
6 道隧集团有限公司
省道215线康定瓦泽至九龙段公路改建工程A5合同段 隧道洞口截水沟工程
措施,把噪音降低到最低限度。
(2)对强噪声机械(如搅拌机、电锯、电刨、砂轮机等)设置封闭的操作棚,以减少噪声扩散。 (3)在施工现场倡导文明施工,尽量减少人为的大声喧哗,不使用高音喇叭或怪音喇叭,增
强全体施工人员防噪声扰民的自觉意识。
(4)尽量避免夜间施工,确有必要时及时向环保部门办理夜间施工许可证,并向周边居民告
示。